G11 level 4 concrete pour


Great progress this week on the Library Extension and Gumurrii Centre (G11) with the level 4 middle compound slab pour.

Watpac provided traffic control on University Drive from 5.30am keeping us all safe and the deliveries coming.

Within 3-4 weeks all the slabs on level 4 will be complete, then the programme will advance quickly. The level 4 middle compound slab will eventually provide a floor for the Sky Lounge, a seminar and meeting room and consultation spaces.