G11 construction – early works programme


The high impact works to carpark B and University Drive continue this week. Anticipated completion (weather permitting) for all works is Friday, February 24.

  • On Wednesday, February 15 temporary concrete footpaths for pedestrian access near G33 and existing equity access parking will be poured.

In G10 this week, four commonuse computer tables in Tech Park will be relocated to the Piazza. All PCs will be back up and running for Monday, February 20. The plasma screen behind service pods 1 and 2 has been reinstalled and will be operational for February 20 as well.

Outside G10 demolition of existing roof faces begins – west face gutters will be removed and exiting roof cut back.

 

Not long now until the G11 client information kiosk is complete with digital signage, a Smartboard to record client comments and take away information sheets. Countdown is on to the return of ‘Demo a donut’ – see you at our first event on Wednesday, February 29 at 10am