N53 construction – on site this week, issue 17


A busy week onsite as our contractors complete demolition works to level 2 external walls, removal of concrete, windows, bulkheads and soffits. They are also installing scaffolding to the north face which will involve drilling into the level 1 slab. Steel work is going in to the level 2 mezzanine floor, with formwork/Bondek and reinforcing also to the floor slab. The next concrete pour is the level 2 mezzanine slab this Thursday/Friday, weather permitting.

Come and see me at our first ‘demo a doughnut’ for the semester on Wednesday morning at 10am. And collect a pair of earplugs if you need them!

Lori (the Donut Lady)